Satunaigawa Dam web site(History of Satunaigawa Dam)
History of Satunaigawa Dam
1971 | Preliminary investigation started |
April 1981 | Planning stage started |
April 1985 | Construction started |
March 1986 | Construction of necessary roads started |
October 1987 | Construction of accessory roads started |
November 1988 | Construction of the dam started |
June 1989 | Excavation of the foundation started |
October 1989 | Redirection of the river flow started |
May 1991 | Concrete pouring started |
September 1991 | Corner stone laid to commemorate construction of the dam |
May 1996 | Pouring of concrete completed(770,000m3) |
December 1996 | Second redirection of river flow started |
April 1997 | Filling test started(ended in December) |
June 1997 | Accessory roads opened |
July 1998 | Completion ceremony held |
April 1999 | Control office opened |
1.Before the dam construction
(September 1985)
(September 1985)
2.Foundation excavation
(May 1990)
(May 1990)
3.Pouring concrete
(October 1994)
(October 1994)
4.Filling test
(June 1997)
(June 1997)